Table of Contents
2.......... Project Information
2.3 Construction Programme and Activities
2.5 Status of Environmental Licences, Notification and Permits
3.......... Environmental Monitoring Requirements
3.1 Construction Dust Monitoring
3.2 Construction Noise Monitoring
4.......... Implementation Status of Environmental Mitigation Measures
5.......... Monitoring Results
5.1 Construction Dust Monitoring
5.2 Regular Construction Noise Monitoring
6.......... ENVIRONMENTAL SITE INSPECTION AND AUDIT
7.......... Environmental Non-conformance
7.1 Summary of Monitoring Exceedances
7.2 Summary of Environmental Non-Compliance
7.3 Summary of Environmental Complaints
7.4 Summary of Environmental Summon and Successful Prosecutions
8.1 Construction Programme for the Next Three Months
8.2 Key Issues for the Coming Month
8.3 Monitoring Schedule for the Coming Month
9.......... ConclusionS AND RECOMMENDATIONS
List of Tables
Table 2.1.......... Construction Activities in the reporting month
Table 2.2.......... Contact Information of Key Personnel
Table 2.3.......... Status of Environmental Licenses, Notifications and Permits
Table 3.1 ........ Air Quality Monitoring Equipment
Table 3.2 ........ Location of Construction Dust Monitoring Station
Table 3.3 ........ Noise Monitoring Parameters, Frequency and Duration
Table 3.4 ........ Noise Monitoring Equipment for Regular Noise Monitoring
Table 3.5 ........ Noise Monitoring Stations during Construction Phase
Table 3.6 ........ Noise Monitoring Parameters, Frequency and Duration
Table 4.1.......... Status of Required Submission under Environmental Permit
Table 5.1 ........ Summary of 24-hour TSP Monitoring Result in the Reporting Period
Table 5.2 ........ Summary of 1-hour TSP Monitoring Result in the Reporting Period
Table 5.3 ........ Summary of Construction Noise Monitoring Results in the Reporting Period
Table 6.1 ........ Observations and Recommendations of Site Audit
Table 8.1.......... Construction Activities in the coming three months
List of Figures
Site Layout Plan |
|
Location of Air Quality Monitoring Station |
|
Locations of Noise Monitoring Station |
|
|
|
List of Appendices
Construction Programme |
|
Project Organization Structure |
|
Implementation Schedule of Environmental Mitigation Measures |
|
Summary of Action and Limit Levels |
|
Calibration Certificates of Equipment |
|
EM&A Monitoring Schedules |
|
Air Quality Monitoring Results and their Graphical Presentations |
|
Noise Monitoring Results and their Graphical Presentations |
|
Event and Action Plan Cumulative Statistics on Complaints, Notification of Summons and Successful Prosecutions |
|
Monthly Summary Waste Flow Table Shatin to Central Link (Hung Hom – Admiralty Section) Kai Tak Barging Facility under FEP-01/436/2012/F Monthly EM&A Report for August 2021 |
|
|
|
Central Kowloon Route – Kai Tak West (CKR-KTW; Contract No. HY/2014/07) (hereafter called “the Project”) covers part of the construction of the Central Kowloon Route (CKR).
The Project comprises the follow works:
· 50x30m access shaft with noise enclosure at Ma Tau Kok (MTK);
· 100m long cut-and-cover (C&C) tunnel at MTK;
· Demolition and re-provisioning of MTK Public Pier;
· 160m long underwater tunnel (UWT) (Stage 1);
· 210m long UWT (Stage 2);
· 60m long C&C tunnel at Kai Tak;
· 130m long depressed road and 200m long underpass at Kai Tak;
· 390m long underground tunnel ventilation adit at Kai Tak;
· Seawall demolition and construction of new landing steps; and
· Barging Point enclosure and conveyor system.
The EM&A programme commenced on 4 April 2018.The impact EM&A for the Project includes air quality and noise monitoring.
This is the 41st monthly EM&A Report presenting the EM&A works carried out during the period between 1 and 31 August 2021. As informed by the Contractor, major activities in the reporting period were:
Locations |
Site Activities |
Kai Tak |
· Wall and roof slab construction at cut & cover, underpass and depressed road; · Backfilling at Underpass and depressed road; · Removal of ELS at cut & cover, underpass and depressed road · Dismantle of working platform |
Ma Tau Kok |
· TTM implementation; · Trial trench for piling works; · Pre-grouting works for pipe piling works for MTK C&C Tunnel; · Pipe piling works for MTK C&C tunnel; · Temporary storm dain diversion works |
Kowloon Bay |
· Bracing and Waling Removal at Stage 1 UWT; · Concrete Packing Breaking at Stage 1 UWT; · Stage 1 Marine Platform Removal for Stage 2 UWT; · Piling Works for Stage 2 UWT; · Erect Marine Platform for Stage 2 UWT |
|
Breaches of Action and Limit Levels for Air Quality
All 24-hour TSP result was below the Action and Limit Levels at all monitoring locations in the reporting month.
All 1-hour TSP result was below the Action and Limit Levels at all monitoring locations in the reporting month.
Breaches of Action and Limit Levels for Noise
Regular Noise Monitoring
No exceedance of Action and Limit Level of noise was recorded
in the reporting month.
Complaint, Notification of Summons and Successful Prosecution
No environmental related complaints, notification of summons and successful prosecution were received
in the reporting month.
Reporting Changes
No report changes in the
reporting period.
Future Key Issues
Key issues to be considered in the next three months included:
Locations |
Site Activities |
Kai Tak |
· Wall and roof slab construction at cut & cover, underpass and depressed road; · Backfilling works and ELS removal at cut & cover, underpass and depressed road; · Dismantle of working platform |
Ma Tau Kok |
· TTM implementation; · Pre-grouting works for pipe piling works of MTK C&C Tunnel · Pipe piling works for cut and cover tunnel; · Temporary storm drain diversion works |
Kowloon Bay |
· Seawall Reinstatement at Stage 1 UWT; · Construction of remaining bulkhead wall at Stage 1 UWT; · Stage 1 Marine Platform Removal for Stage 2 UWT; · Piling Works at Stage 2 UWT; · Marine King Post and Access Platform Construction; · Temporary Reclamation & Wall Tie Installation at Stage 2 UWT |
· Section 1: Introduction
· Section 2: Project Information
· Section 3: Environmental Monitoring Requirement
· Section 4: Implementation Status of Environmental Mitigation Measures
· Section 5: Monitoring Results
· Section 6: Environmental Site Inspection and Audit
· Section 7: Environmental Non-conformance
· Section 8: Future Key Issues
· Section 9: Conclusions and Recommendations
(a) construction of approximately 160m long cut-and-cover tunnel and 370m long underwater tunnel between the tunnel section at Ma Tau Kok and the depressed road of the CKR within Kai Tak Development;
(b) reconstruction of the seawall at Ma Tau Kok public pier, and the sloping seawall at the Former Kai Tak Airport Runway;
(c) construction of approximately 125m long depressed road and 200m long underpass of the CKR within Kai Tak Development;
(d) construction of approximately 360m long underground tunnel ventilation adit of the CKR;
(e) reconstruction of Kowloon City Ferry Pier Public Transport Interchange; and
(f) other associated works.
Table 2.1 Construction Activities in the reporting month
Locations |
Site Activities |
Kai Tak |
· Wall and roof slab construction at cut & cover, underpass and depressed road; · Backfilling at Underpass and depressed road; · Removal of ELS at cut & cover, underpass and depressed road · Dismantle of working platform |
Ma Tau Kok |
· TTM implementation; · Trial trench for piling works; · Pre-grouting works for pipe piling works for MTK C&C Tunnel; · Pipe piling works for MTK C&C tunnel; · Temporary storm dain diversion works |
Kowloon Bay |
· Bracing and Waling Removal at Stage 1 UWT; · Concrete Packing Breaking at Stage 1 UWT; · Stage 1 Marine Platform Removal for Stage 2 UWT; · Piling Works for Stage 2 UWT; · Erect Marine Platform for Stage 2 UWT |
|
Table 2.2 Contact Information of Key Personnel
Party |
Role |
Position |
Name |
Telephone |
Fax |
Arup-Mott MacDonald Joint Venture |
Residential Engineer (ER) |
Engineer’s Representative |
Mr. Jeffrey Lau |
2268 3640 |
2268 3954 |
ERM |
Independent Environmental Checker (IEC) |
Independent Environmental Checker |
Ms. Mandy To |
2271 3313 |
2723 5660 |
Gammon |
Contractor |
Contracts Manager |
Mr. Alan Yan |
2516 8823 |
2516 6260 |
Environmental Manager |
Ms Michelle Tang |
9267 8866 |
2516 6260 |
||
AECOM |
Contractor’s Environmental Team (ET) |
ET Leader |
Mr. Y T Tang |
3922 9393 |
2317 7609 |
Table 2.3 Status of Environmental Licenses, Notifications and Permits
Permit / License No. / Notification/ Reference No. |
Valid Period |
Status |
Remarks |
|
From |
To |
|||
Further Environmental Permit |
||||
FEP-01/457/2013/C |
28 Feb 2018 |
End of Project |
Valid |
-- |
Wastewater Discharge License |
||||
WT00030290-2018 |
22 Mar 2018 |
31 May 2023 |
Valid |
Ma Tau Kok |
WT00030668-2018 |
27 Apr 2018 |
30 Apr 2023 |
Valid |
Site Office at Kai Tak West |
WT00030358-2018 |
27 Apr 2018 |
30 Apr 2023 |
Valid |
Kai Tak West |
WT00030330-2018 |
27 Apr 2018 |
30 Apr 2023 |
Valid |
Kowloon Bay |
Construction Noise Permit |
||||
GW-RE0355-21 |
4 May 2021 |
3 Aug 2021 |
Valid until 3 Aug 2021 and Superseded |
General Works at Ma Tau Kok |
GW-RE0732-21 |
3 Aug 2021 |
2-Feb-2022 |
Valid |
|
GW-RE0658-21 |
11 Jul 2021 |
10 Jan 2022 |
Valid |
General Works at Kai Tak |
GW-RE0474-21 |
21 May 2021 |
20 Nov 2021 |
Valid |
ELS Removal at Stage 1 UWT |
PP-RE0018-21 |
3 Jun 2021 |
2 Aug 2021 |
Valid until 2 Aug 2021 and Superseded |
Percussive Piling at Stage 2 Underwater Tunnel |
PP-RE0027-21 |
2 Aug 2021 |
31 Jan 2022 |
Valid |
|
GW-RE0259-21 |
1 Apr 2021 |
30 Sep 2021 |
Valid |
Kai Tak Haul Road |
Chemical Waste Producer Registration |
||||
5118-247-G2347-47 |
30 Jan 2018 |
End of Project |
Valid |
-- |
5118-247-G2347-48 |
30 Jan 2018 |
End of Project |
Valid |
-- |
Marine Dumping Permit |
||||
-- |
-- |
-- |
-- |
-- |
Billing Account for Construction Waste Disposal |
||||
7029909 |
22 Jan 2018 |
End of Project |
Account Active |
-- |
7031949 |
27 May 2021 |
26 Aug 2021 |
Account Active until 26 Aug 2021 |
Billing Account for Disposal of Construction Waste (by vessels) |
27 Aug 2021 |
25 Nov 2021 |
Account Active |
||
Notification Under Air Pollution Control (Construction Dust) Regulation |
||||
429442 |
5 Jan 2018 |
5 Jul 2025 |
Notified |
-- |
|
Monitoring Requirements
Monitoring Equipment
Table 3.1 Air Quality Monitoring Equipment
Tisch Total Suspended Particulate Mass Flow Controlled High
Volume Air Sampler |
|
Calibration Kit (24-hour TSP) |
TISCH Environmental Orifice |
Portable direct reading dust meter |
Sibata Digital Dust Monitor |
Monitoring Locations
Table 3.2 Location of Construction Dust Monitoring Station
Location |
Monitoring Station |
Description |
E-A14a [1] |
Block B of Merit Industrial Centre |
Rooftop (13/F) |
[1] The air monitoring station proposed in the EM&A Manual (i.e. Wyler Gardens with ID: E-A14) was not available for impact dust monitoring, therefore impact monitoring was conducted at E-A14a as an alternative which was agreed by the ER, IEC and EPD.
Monitoring Methodology
(a) The HVS was installed in the vicinity of the air sensitive receivers. The following criteria were considered in the installation of the HVS as far as practicable: -
(i) A horizontal platform with appropriate support to secure the sampler against gusty wind was provided.
(ii) Two samplers should not be placed less than 2m apart from each other;
(iii) The distance between the HVS and any obstacles, such as buildings, was at least twice the height that the obstacle protrudes above the HVS.
(iv) A minimum of 2 meters separation from walls, parapets and penthouse for rooftop sampler.
(v) A minimum of 2 meters separation from any supporting structure, measured horizontally is required.
(vi) No furnace or incinerator flues nearby.
(vii) Airflow around the sampler was unrestricted.
(viii) The sampler was located more than 20 meters from any dripline.
(ix) Any wire fence and gate, required to protect the sampler, did not obstruct the monitoring process.
(x) Permission was obtained to set up the samplers and access to the monitoring station.
(xi) A secured supply of electricity was obtained to operate the sampler.
(b) Preparation of Filter Papers
(i) Glass fibre filters, G810 were labelled and sufficient filters that were clean and without pinholes were selected.
(ii) All filters were equilibrated in the conditioning environment for 24 hours before weighing. The conditioning environment temperature was around 25 °C and not variable by more than ±3 °C; the relative humidity (RH) was < 50% and not variable by more than ±5%. A convenient working RH was 40%.
(iii) All filter papers were prepared and analysed by ALS Technichem (HK) Pty Ltd., which is a HOKLAS accredited laboratory and has comprehensive quality assurance and quality control programmes.
(c) Field Monitoring
(i) The power supply was checked to ensure the HVS works properly.
(ii) The filter holder and the area surrounding the filter were cleaned.
(iii) The filter holder was removed by loosening the four bolts and a new filter, with stamped number upward, on a supporting screen was aligned carefully.
(iv) The filter was properly aligned on the screen so that the gasket formed an airtight seal on the outer edges of the filter.
(v) The swing bolts were fastened to hold the filter holder down to the frame. The pressure applied was sufficient to avoid air leakage at the edges.
(vi) Then the shelter lid was closed and was secured with the aluminium strip.
(vii) The HVS was warmed-up for about 5 minutes to establish run-temperature conditions.
(viii) A new flow rate record sheet was set into the flow recorder.
(ix) On site temperature and atmospheric pressure readings were taken and the flow rate of the HVS was checked and adjusted at around 1.3 m3/min, and complied with the range specified in the EM&A Manual (i.e. 0.6-1.7 m3/min).
(x) The programmable digital timer was set for a sampling period of 24 hrs, and the starting time, weather condition and the filter number were recorded.
(xi) The initial elapsed time was recorded.
(xii) At the end of sampling, on site temperature and atmospheric pressure readings were taken and the final flow rate of the HVS was checked and recorded.
(xiii) The final elapsed time was recorded.
(xiv) The sampled filter was removed carefully and folded in half length so that only surfaces with collected particulate matter were in contact.
(xv) It was then placed in a clean envelope and sealed.
(xvi) All monitoring information was recorded on a standard data sheet.
(xvii) Filters were then sent to ALS Technichem (HK) Pty Ltd. for analysis.
(d) Maintenance and Calibration
(i) The HVS and its accessories were maintained in good working condition, such as replacing motor brushes routinely and checking electrical wiring to ensure a continuous power supply.
(ii) HVSs were calibrated using TE-5025A Calibration Kit upon installation and thereafter at bi-monthly intervals.
(iii) Calibration certificate of the TE-5025A Calibration Kit and the HVSs are provided in Appendix E.
(a) Measuring Procedures
The measuring procedures of the 1-hour dust meter are in accordance with the Manufacturer’s Instruction Manual as follows:
(i) Turn the power on.
(ii) Close the air collecting opening cover.
(iii) Push the “TIME SETTING” switch to [BG]
(iv) Push “START/STOP” switch to perform background measurement for 6 seconds.
(v) Turn the knob at SENSI ADJ position to insert the light scattering plate.
(vi) Leave the equipment for 1 minute upon “SPAN CHECK” is indicated in the display.
(vii) Push “START/STOP” switch to perform automatic sensitivity adjustment. This measurement takes 1 minute.
(viii) Pull out the knob and return it to MEASURE position.
(ix) Push the “TIME SETTING” switch the time set in the display to 3 hours.
(x) Lower down the air collection opening cover.
(xi) Push “START/STOP” switch to start measurement.
(b) Maintenance and Calibration
(i) The 1-hour TSP meter was calibrated at 1-year intervals against a continuous particulate TEOM Monitor, Series 1400ab. Calibration certificates of the Laser Dust Monitors are provided in Appendix E.
Monitoring Schedule for the Reporting Month
Monitoring Requirements
Table 3.3 Noise Monitoring Parameters, Frequency and Duration
Parameter and Duration |
Frequency |
30-mins measurement at each monitoring station between 0700 and 1900 on normal weekdays. Leq, L10 and L90 would be recorded. |
At least once per week |
Table 3.4 Noise Monitoring Equipment for Regular Noise Monitoring
B&K (Model No. 2250 & 2238) |
|
Acoustic Calibrator |
Rion (Model No. NC-74) & B&K (Model No. 4231) |
Monitoring Locations
Table 3.5 Noise Monitoring Stations during Construction Phase
Location |
Monitoring Station |
Description |
Measurement |
E-N12a [1] |
19 Hing Yan Street |
Rooftop (9/F) |
Façade |
E-N21a [1] |
Block B of Merit Industrial Centre |
Rooftop (13/F) |
Free field[2] |
Notes:
[1] The noise monitoring stations proposed in the EM&A Manual (i.e. Grand Waterfront Tower 3 with ID: E-N12 and Hang Chien Court Block J with ID: E-N21) were not available for impact noise monitoring, therefore impact monitoring was conducted at E-N12a and E-N21a as an alternative which was agreed by the ER, IEC and EPD.
[2] A correction of +3 dB(A) was made to the free field measurements.
Monitoring Parameters, Frequency and Duration
Table 3.6 Noise Monitoring Parameters, Frequency and Duration
Location |
Parameter and Duration |
Frequency |
E-N12a and E-N21a |
30-mins measurement at each monitoring station between 0700 and 1900 on normal weekdays. Leq, L10 and L90 would be recorded. |
At least once per week |
Monitoring Methodology
(a) The sound level meter was set on a tripod at a height of 1.2 m above the ground.
(b) Façade measurement was made at E-N12a.
(c) Free field measurements was made at monitoring location E-N21a. A correction of +3 dB(A) shall be made to the free field measurements.
(d) The battery condition was checked to ensure the correct functioning of the meter.
(e) Parameters such as frequency weighting, the time weighting and the measurement time were set as follows:
(i) frequency weighting
(ii) time weighting: Fast
(iii) time measurement: Leq(30-minutes) during non-restricted hours i.e. 0700 – 1900 on normal weekdays.
(f) Prior to and after each noise measurement, the meter was calibrated using the acoustic calibrator for 94 dB(A) at 1000 Hz. If the difference in the calibration level before and after measurement was more than 1 dB(A), the measurement would be considered invalid and repeat of noise measurement would be required after re-calibration or repair of the equipment.
(g) During the monitoring period, the Leq, L10 and L90 were recorded. In addition, site conditions and noise sources were recorded on a standard record sheet.
(h) Noise measurement was paused during periods of high intrusive noise (e.g. dog barking, helicopter noise) if possible. Observations were recorded when intrusive noise was unavoidable.
(i) Noise monitoring was cancelled in the presence of fog, rain, wind with a steady speed exceeding 5m/s, or wind with gusts exceeding 10m/s.
(a) The microphone head of the sound level meter was cleaned with soft cloth at regular intervals.
(b) The meter and calibrator were sent to the supplier or HOKLAS laboratory to check and calibrate at yearly intervals.
(c) Calibration certificates of the sound level meters and acoustic calibrators are provided in Appendix E.
Monitoring Schedule for the Reporting Month
Table 4.1 Status of Required Submission under Environmental Permit
EP Condition |
Submission |
Submission Date |
Condition 3.4 of
|
Monthly EM&A Report for July 2021 |
13 August 2021 |
Table 5.1 Summary of 24-hour TSP Monitoring Result in the Reporting Period
ID |
Average (mg/m3) |
Range (mg/m3) |
Action Level (mg/m3) |
Limit Level (mg/m3) |
E-A14a |
22.5 |
15.5 – 36.4 |
197.3 |
260 |
Table 5.2 Summary of 1-hour TSP Monitoring Result in the Reporting Period
ID |
Average (mg/m3) |
Range (mg/m3) |
Action Level (mg/m3) |
Limit Level (mg/m3) |
E-A14a |
61.1 |
57.8 – 62.3 |
302.4 |
500 |
Table 5.3 Summary of Construction Noise Monitoring Results in the Reporting Period
ID |
Range, dB(A), Leq (30 mins) |
Limit Level, dB(A), Leq (30 mins) |
E-N12a |
63.7 – 67.4 |
75 |
E-N21a |
62.1 – 67.9 |
75 |
Table 6.1 Observations and Recommendations of Site Audit
Parameters |
Date |
Observations and Recommendations |
Follow-up |
Air Quality |
11 Aug 2021 |
· Emission of dark smoke was observed at drilling rig at Ma Tau Kok. The Contractor was advised to maintain the drilling rig properly. |
The item was rectified by the Contractor on 18 Aug 2021. |
18 Aug 2021 |
Reminder: · The Contractor was reminded to provide water regularly at Kai Tak. |
The item was rectified by the Contractor on 25 Aug 2021. |
|
25 Aug 2021 |
Reminder: · The contractor was reminded to cover the dusty materials to avoid dust emission at Ma Tau Kok. |
The item was rectified by the Contractor on 1 Sep 2021. |
|
Noise |
11 Aug 2021 |
Reminder: · The Contractor was reminded to enclose the noise barrier for the water pump at Ma Tau Kok properly |
The item was rectified by the Contractor on 18 Aug 2021. |
Water Quality |
18 Aug 2021 |
· High pH value was observed at AquaSed at Ma Tau Kok. The contractor should adjust the pH as required in the discharge license. |
The item was rectified by the Contractor on 25 Aug 2021. |
25 Aug 2021 |
Reminder: · The contractor was advised to maintain the pH value of AquaSed at Ma Tau Kok as required in the water discharge license. |
The item was rectified by the Contractor on 1 Sep 2021. |
|
Waste/ Chemical Management |
Nil |
Nil |
Nil |
Landscape & Visual |
Nil |
Nil |
Nil |
Permits/ Licenses |
Nil |
Nil |
Nil |
Table 8.1 Construction Activities in the coming three months
Locations |
Site Activities |
Kai Tak |
· Wall and roof slab construction at cut & cover, underpass and depressed road; · Backfilling works and ELS removal at cut & cover, underpass and depressed road; · Dismantle of working platform |
Ma Tau Kok |
· TTM implementation; · Pre-grouting works for pipe piling works of MTK C&C Tunnel · Pipe piling works for cut and cover tunnel; · Temporary storm drain diversion works |
Kowloon Bay |
· Seawall Reinstatement at Stage 1 UWT; · Construction of remaining bulkhead wall at Stage 1 UWT; · Stage 1 Marine Platform Removal for Stage 2 UWT; · Piling Works at Stage 2 UWT; · Marine King Post and Access Platform Construction; · Temporary Reclamation & Wall Tie Installation at Stage 2 UWT |
Chemical and Waste Management